How to Install Substation Arresters

How to Install Substation Arresters.

arresters-general-1.jpg
  1. To install substation arresters, follow the directions, recommended work practices and be safe.
  2. Inspect the packaging and product, looking for signs of damage.
  3. Verify kV rating on nameplate, carton/crate label and shipping documents all agree.  If they do not, stop and contact Hubbell Power Systems, Inc. prior to installation.
  4. Locate and read all installation instructions included with the packaging. If there are any questions, now is the time to ask. 
  5. Prior to starting installation verify all hardware is included.arresters-general-1.jpg
  6. Testing is not required prior to installation.
  7. Tighten all fasteners to the values in the installation instructions.
  8. For porcelain arresters point the directional vents away from other equipment.
  9. The stacking order of multi-unit arresters is very important. Verify the proper stacking order by reviewing the outline drawing with the packaging and the nameplate on the bottom unit.
  10. The use of any included grading ring is critical to life of the arrester. Verify the need for a ring by reviewing the outline drawing with the packaging.
  11. Hubbell Power Systems supplies stacking bolts but since mounting surfaces vary in thickness mounting bolts are not included. Grade 5 bolts should be used for mounting.

JOIN AN UPCOMING ARRESTER WEBINAR



Recommended Posts

pcore hv oil-free prc bushings

Get High Performance with New PCORE® High-Voltage PRC® Bushings

Continue Reading
 Barry D.E.W. Line® Insulating Tag Lines

Enhance Safety During Live-Line Maintenance With Barry D.E.W. Line® Insulating Tag Lines

Continue Reading
Hubbell Polymer Deadend Insulators

Hubbell Polymer Deadend Insulators: The Industry Go-To

Continue Reading
Ï